Study on Blasting Vibration and Fragmentation Control of Underground Powerhouse based on Time-sequence Effect of Millisecond Delay Initiation
摘要
地下厂房爆破开挖过程中,为保护岩锚梁等关键构筑物,往往采用较大微差间隔时间来避免爆破振动峰值叠加,但也导致爆破后大块率偏高的问题,为此基于微差爆破技术开展了振动控制与块度优化研究.基于爆破振动线性叠加原理,建立了考虑孔数与岩体衰减特性的振动放大系数模型,推导出了满足不同距离振动安全阈值的临界微差间隔时间计算公式.以旭龙水电站地下厂房开挖为工程背景,通过现场试验验证了理论模型的适用性.研究结果表明:相较于100 ms微差间隔方案,优化后的50 ms微差间隔方案能将岩锚梁岩台处的爆破振动速度峰值控制在2.8 cm/s,同时,该方案显著改善了爆破块度,使中值粒径由约75.5 cm降低至11.3 cm,级配均匀性显著提升,大块率有效降低.研究为解决地下工程爆破中振动安全与破碎效果的矛盾提供了理论依据和一种可行的临界微差时间选择方法.
During underground powerhouses blasting excavation,extended inter-hole delay times are commonly employed to safeguard critical structures like rock-anchored beams by preventing blast vibration peak superposition.This method,however,results in elevated boulder rates.To address this issue,vibration control and fragmentation op-timization studies were conducted using millisecond blasting techniques.Using the linear superposition principle for blast vibrations,this study established a vibration amplification factor model that incorporates the number of holes and rock mass attenuation properties,and derived a computational formula for critical inter-hole delay times that meet vi-bration safety thresholds at varying distances.Field validation tests were conducted during the excavation of Xulong Hydropower Station's underground powerhouse,confirming the theoretical model's practical applicability.Results demonstrate that the optimized 50 ms inter-hole delay scheme,compared to the conventional 100 ms approach,main-tains peak particle velocity at rock-anchored beam benches below 2.8 cm/s while achieving superior fragmentation performance.This configuration reduces the median fragment size from approximately 75.5 cm to 11.3 cm,signifi-cantly improving size-distribution uniformity and effectively minimizing boulder occurrence.The research establishes both theoretical foundations and practical methodologies for determining critical delay intervals to reconcile vibration safety and fragmentation quality in underground blasting operations.