摘要 露天矿山高陡边坡施工中,预裂爆破是控制边坡稳定与轮廓质量的核心技术,传统预裂爆破施工工艺普遍采用"导爆索+竹片+32 mm乳化炸药"构成轴向间隔径向不耦合装药结构,存在孔距小、钻孔量大、药包制作繁琐、装药可靠性差等问题,导致循环作业时间长、综合成本高、半孔率不稳定等情况.为改善上述工程问题,提出了一种基于普通PVC管的新型高陡边坡预裂爆破装药方法,该方法将直径40~50 mm的普通PVC管预先安装于炮孔(115 mm)内,形成规整的不耦合空间,装药时直接向管内装填32 mm乳化炸药并利用1~2发电子雷管起爆.以英德某石英砂岩矿、阳西某片麻岩矿、揭阳某花岗岩建筑石材矿、开平某粉砂岩建材矿为依托开展工程试验,结果表明:①新技术将孔距扩大至2.0~2.2 m,较传统方法钻孔消耗量减少33%~46%;②取消了"导爆索+竹片+药卷"等施工环节后,预裂爆破作业时间可降低47%;③简化施工工艺和耗材后预裂爆破综合成本降低约42%;④软岩半孔率65%~85%,硬岩半孔率95%,较传统工艺提高5%~13%,且爆破效果(半孔率)稳定性更好.该方法在保障预裂爆破质量同时实现了效率与经济性的双重提升,对类似露天矿山边坡施工具有指导意义.
Abstract:
Presplit blasting serves as a fundamental technique for maintaining slope stability and ensuring con-tour precision during high-steep slope construction in open-pit mines.Conventional presplitting methods typically em-ploy an axially spaced and radially decoupled charge configuration using detonating cords,bamboo spacers,and 32 mm emulsion explosives.Nevertheless,this conventional approach presents operational challenges including re-stricted borehole spacing,excessive drilling requirements,labor-intensive charge preparation,and inconsistent char-ging reliability.These operational deficiencies result in prolonged construction cycles,elevated project costs,and in-consistent half-hole preservation rates.To address these technical challenges,an innovative presplit blasting tech-nique using standard PVC piping is developed for steep slope applications.The method involves 40~50 mm diameter PVC conduits with 115 mm blast holes to create precise decoupling spaces,followed by direct loading of 32 mm e-mulsion explosives into the pipes with 1~2 electronic detonators for initiation.Field validations were successfully conducted across multiple geological formations including quartz sandstone at Yingde,gneiss at Yangxi,granite di-mension stone at Jieyang,and siltstone construction material deposits at Kaiping.The results demonstrate that:(1)The novel technique enables borehole spacing expansion to 2.0~2.2 m,achieving 33%~46%reduction in drill-ing consumption compared to traditional method;(2)Eliminating of complex construction components(detonating cords,bamboo spacers,and explosive rolls)reduces presplit blasting operation time by 47%;(3)Streamlined construc-tion processes and material requirements yield approximately 42%lower overall costs;(4)Half-hole factor reached 65%~85%in soft rocks and 95%in hard rock formations,representing 5%~13%improvement over traditional tech-niques with enhanced effect stability.This methodology guarantees presplit blasting quality while simultaneously impro-ving efficiency and cost-effectiveness,providing valuable guidance for analogous open-pit slope engineering projects.
刊 名 爆破 ISTICPKU
年,卷(期): 2026, 43(3)
分类号: TD235.3
机标分类号: TD235 U455.6 TD824.2
在线出版日期: 2026年10月13日