摘要
[目的]为提高特高压直流六分裂跳线线长的计算精度,高效实现跳线的装配式安装,提出了一种耐张串末端倾斜角和跳线长度的精确计算方法.[方法]以导线水平张力为基准逐个分析各连接元件倾斜角,通过循环迭代方法计算耐张串的末端倾斜角;建立基于三维坐标系的通用计算模型,以软跳线子导线平弧垂一致为条件,利用悬链线公式计算跳线长度;采用有限元模拟、AutoCAD三维建模和现场实测方法验证耐张串末端倾斜角计算方法、通用计算模型和跳线长度计算方法的准确性.[结果]所提循环迭代方法经过4次迭代后末端倾斜角已稳定,倾斜角的计算结果与有限元模拟值吻合;所提通用计算模型获得的各跳线悬挂安装点位置与AutoCAD绘图模拟位置一致;某实际跳线装配式安装后,经全站仪与无人机测量结果复核,现场实测值与计算值吻合;某跳线案例表明装配式安装相比高空模拟法,高空作业量减少46.4%,工效提高25%,人工节约33.3%.[结论]所提耐张串倾斜角迭代计算方法比传统的将耐张串等效为均布自重荷载方法更准确;编写的六分裂跳线长度计算通用程序,图形交互性好,具有较强的实用性与便捷性;实现了特高压直流六分裂大截面导线跳线的装配式安装,达到了减少高空作业量、提升施工效率、降低导线损耗和保障施工工艺质量的目的.
[Objective]To improve the calculation accuracy of the jumper length for six-bundle jumpers in ultra-high voltage direct current(UHVDC)transmission lines and to efficiently achieve prefabricated installation of the jumpers,a precise calculation method for the inclination angle at the end of the tension string and the jumper length is proposed.[Methods]Taking the horizontal tension of the conductor as the reference,the inclination angles of individual connecting components are analyzed sequentially,and the inclination angle at the end of the tension string is calculated using an iterative method.A general calculation model based on a three-dimensional coordinate system is established,and the jumper length is calculated using the catenary formula under the condition that the sag of each sub-conductor of the flexible jumper is uniform.The accuracy of the inclination angle at the end of the tension string,the general calculation model,and the jumper length calculation method is verified using finite element simulation,three-dimensional modeling in AutoCAD,and field measurements.[Results]The proposed iterative method achieves a stable terminal inclination angle after four iterations,and the calculated inclination angles are in good agreement with the finite element simulation results.The suspension points of each jumper obtained using the proposed general calculation model are consistent with the simulated positions generated by AutoCAD modeling.After the prefabricated installation of an actual jumper,field measurements obtained via total station and drone surveys closely matched the calculated values.A jumper installation case demonstrates that,compared with the traditional high-altitude simulation method,the prefabricated approach reduces high-altitude workload by 46.4%,increases work efficiency by 25%,and reduces labor costs by 33.3%.[Conclusions]The proposed iterative method for calculating the inclination angle of the tension string is more accurate than the traditional method that simplifies the tension string as a uniformly distributed self-weight load.The general-purpose program developed for calculating the length of six-bundle jumpers features good graphical user interaction and offers strong practicality and convenience.The prefabricated installation of six-bundle large-cross-section conductor jumpers for UHVDC transmission lines has been successfully realized,achieving the objectives of reducing high-altitude workload,improving construction efficiency,minimizing conductor loss,and ensuring high quality of construction technology.