富水地层下叠落盾构隧道施工关键技术及其管理研究
Key Technologies and Supervision Management of Stacked Shield Tunnel Construction in Water-rich Strata
摘要 针对叠落盾构隧道在始发接收及掘进过程中,面临结构承载要求高、地层扰动控制难、易发生突水涌水等质量安全难题,以南京地铁6 号线岗子村站及相邻叠落区间为背景,为有效控制施工风险、保障工程安全和工期要求,采用叠式始发接收复合支撑体系、端头及叠线段土体注浆加固、移动同步支撑台车等多重技术与管理措施.结果表明:后浇始发接收中板最大变形控制在 5 mm 以内,地表最大沉降为19.1 mm,周边建筑物及既有4 号线隧道变形均控制在限值范围内,较传统工艺缩短工期20%.通过采用复合支撑体系与同步支撑台车等技术措施,并严格落实相应的施工与监督管理要点,可有效控制叠式始发接收与掘进施工过程中的质量安全风险.
Abstract:
Taking the Gangzicun Station and its adjacent stacked section of Nanjing Metro Line 6 as the engineering background,which is located in water-rich strata,featuring a long stacked section and long-distance parallel alignment with an existing operational line,key technologies and supervision management of stacked shield tunnel construction were proposed and evaluated.During the initiation,reception,and excavation of the stacked shield tunnel,the project faces quality and safety challenges including high structural bearing requirements,difficult ground disturbance control,and high risk of water inrush.To effectively control construction risks and ensure engineering safety and schedule re-quirements,multiple technical and management measures were adopted,including the stacked initiation-reception sup-port system,grouting reinforcement for tunnel ends and stacked sections,and mobile synchronous support trolleys.The engineering implementation results show that the maximum deformation of the post-cast initiation-reception middle slab was controlled within 5 mm,the maximum ground surface settlement was 19.1 mm,and the deformations of surround-ing buildings and the existing Metro Line 4 tunnel were all kept within allowable limits,with the construction period shortened by 20%compared with traditional methods.The research indicates that by adopting technical measures such as the composite support system and synchronous support trolley,and strictly implementing corresponding construction and supervision key points,the quality and safety risks during stacked initiation,reception,and excavation can be ef-fectively controlled.
年,卷(期): 2026, 24(4)
分类号: U455.43 U455.1
机标分类号: U455.43 U231.3 TU433
在线出版日期: 2026年8月25日
基金项目: 2023ZD073:江苏省建设系统科技项目,