Voltage feedforward control method for grid-forming converters in long-distance interconnection scenarios
摘要
针对长距离链式供电系统中远端负荷电压受线路压降影响显著、常规控制难以有效补偿的问题,提出一种计及线路距离的构网型变流器压降前馈控制方法.建立由2台构网型链式互联装备、10 kV交流线路和远端负荷组成的仿真模型,分析线路阻抗、电流变化与负荷端电压之间的关系;在常规虚拟同步发电机控制框架中加入线路压降前馈支路,根据线路参数、供电距离和线路电流估算远端压降补偿量,并经限幅后叠加至电压参考端.进一步,结合负荷端最低电压、源端电压指令峰值和前馈补偿限幅裕度约束,对前馈补偿系数进行选取,并通过小信号特征值分析验证所选参数的稳定性及可接受性.设置近负荷侧装备G2退出和远端负荷阶跃增加2类工况,并采用扰动后0.5 s统一观察窗内的电压跌落面积评价动态电压支撑效果.结果表明,在G2退出工况下,前馈控制将电压跌落面积由113.06 V·s降低至72.88 V·s,降幅为35.53%;在负荷阶跃工况下,电压跌落面积由57.00 V·s降低至40.63 V·s,降幅为28.73%.基于MATLAB/Simulink平台对所提方法与常规VSG控制进行对比验证,仿真结果表明所提方法能够减小运行方式切换及负荷突增过程中的综合欠压程度,提高长距离链式供电系统扰动初期的动态电压支撑能力.
To address the problem that the remote load voltage in a long-distance chained power supply system is significantly affected by line voltage drops,and the conventional control is difficult to effectively compensate,a voltage-drop feedforward control method for grid-forming converters considering line distance is proposed.A simulation model consisting of two grid-forming chained interconnection units,a 10 kV AC line,and a remote load is established to analyze the relationship among line impedance,current variation,and load-side voltage.On this basis,a line-voltage-drop feedforward branch is added to the conventional virtual synchronous generator(VSG)control framework.The remote voltage-drop compensation is estimated according to line parameters,supply distance,and line current,and the saturated compensation value is superimposed on the voltage reference.Furthermore,the feedforward compensation coefficient is selected by considering the constraints of the minimum load-side voltage,the peak source-side voltage command,and the feedforward compensation saturation margin.Small-signal eigenvalue analysis is also conducted to verify the acceptable stability of the selected parameter.Two disturbance scenarios are considered,including the disconnection of the near-load-side unit G2 and a step increase in the remote load.The voltage-deficit area within a unified 0.5 s observation window after each disturbance is adopted to evaluate the dynamic voltage support performance.Under the G2 disconnection scenario,the proposed feedforward control reduces the voltage-deficit area from 113.06 V·s to 72.88 V·s,corresponding to a reduction of 35.53%.Under the load-step scenario,the voltage-deficit area decreases from 57.00 V·s to 40.63 V·s,representing a reduction of 28.73%.Comparative simulations of the proposed method and conventional VSG control were conducted on the MATLAB/Simulink platform.The results demonstrate that the proposed method can mitigate the overall severity of undervoltage during operating-mode transitions and sudden load increases,thereby enhancing the initial dynamic voltage support capability of long-distance chained power supply systems.