军事知识服务平台
双线盾构隧道近距离侧穿桩基方案优选
CASE OPTIMIZATION FOR CONSTRUCTION OF DOUBLE-LINE SHIELD TUNNELS ADJACENT TO PILES
摘要 为解决软弱土层中双线盾构隧道近距离侧穿公路立交桥桩基的安全与经济性问题,开展施工技术方案的优选研究.选取地层损失率、地层加固区域、地层加固强度及双线隧道施工顺序作为关键影响因素,每个因素确定 3 种取值,依据四因素三水平正交设计表构建 9 种施工方案,并对其施工效果进行三维数值模拟分析.引入灰色关联度分析法,建立了涵盖隧道收敛与桩基变形的多指标安全评价模型.首先通过对模拟方案的关联度分析,得出安全度最高的方案,然后结合经济性的要求优选出安全可靠、经济合理的最佳施工方案.现场实施与监测结果显示,施工引起的桥墩竖向位移最大值为0.5 mm,最大倾斜率为 0.2 ‰,均未超过预警值.研究结果证实,基于灰色关联度分析优选的施工方案实现了施工安全与经济效益的协调统一.
Abstract:
To address the safety and economic issues in the construction of a double-line shield tunnel side-crossing a highway overpass pile foundation in soft soil,an optimization study on construction cases was conducted.The ground loss rate,ground reinforcement zone,ground reinforcement strength,and construction sequence of the twin tunnels were selected as the key influencing factors.Three levels were assigned to each factor,and a four-factor,three-level orthogonal array was employed to formulate nine construction cases.Subsequently,three-dimensional numerical simulations were conducted to analyze the construction effects of these cases.Grey relational analysis was introduced to establish a multi-indicator safety evaluation model,incorporating tunnel convergence and pile deformation.Through relational analysis of the simulated cases,the safest option was initially identified.Subsequently,by incorporating economic requirements,the optimal construction case was determined to ensure both safety and economic efficiency.Field implementation and monitoring results showed that the maximum vertical displacement and inclination rate of the piers induced by construction were 0.5 mm and 0.2 ‰,respectively.Neither exceeded the warning thresholds.The results demonstrate that the construction case optimized via grey relational analysis successfully harmonized safety and economic benefits.
刊 名 建筑技术
年,卷(期): 2026, 57(20)
分类号: TU43
机标分类号: TU473 TU741 U455.43
在线出版日期: 2026年10月30日
基金项目: 42272313:国家自然科学基金42672394:国家自然科学基金,