Key Construction Techniques of Steel Box Cofferdam for East Tower Pier of Liuwudian Channel Bridge of Xiamen-Jinmen Bridge
摘要
厦金大桥刘五店航道桥为(130+380+928+380+130)m双塔三跨吊五跨连续悬索桥,东塔墩哑铃型承台采用钢吊箱围堰施工.该围堰平面尺寸为107.8m×49.0m,高14.8m,总重约4024t,采用一体化设计、分幅吊装工艺施工.施工中,钢吊箱围堰采用分幅拼装、滚装装船、分幅运输,降低了场内转运难度;采用动力模块运输车及驳船尾部滚装工艺,提升了滚装效率并降低了船舶倾覆风险;通过一体化整体加工与分幅吊装下放,加快了施工进度,实现了围堰快速精准就位;采用左、右幅分幅吊装就位工艺,通过导向限位、临时拉杆预紧及水下焊接完成左、右幅对接,有效减少了大型设备投入与施工成本.左、右幅钢吊箱围堰安装就位后,接口处错台仅5mm,纵、横、竖向偏位分别为1.6、2.1、2.6cm,均满足设计要求.
The Liuwudian Channel Bridge of Xiamen-Jinmen Bridge is a two-tower suspension bridge arranged in three suspended spans of 380 m,928 m,and 380 m,and two end spans of 130 m.The dumbbell-shaped pile cap of east tower pier was constructed with the assistance of a steel box cofferdam that measures 107.8 m by 49.0 m,14.8 m in height,with a total weight of 4 024 t.The cofferdam was integratedly designed and erected segment by segment.Techniques,including segmented assembly,roll-on/roll-off shipment,and segmented transportation,were taken to facilitate the transportation of the steel box cofferdam.The self-propelled modular transporter was employed,and the segments were rolled on and off from the stern of the barge,to improve the shipment efficiency and reduce the barge capsizing risk.The cofferdam was rapidly and accurately located.The left and right halves of the cofferdam were butt-joined by restrainers,temporary tensile rods and underwater welding,minimizing the equipment investment and costs.After the installation of the left and right halves,the staggering of the joint is only 5 mm.The longitudinal,transverse and vertical deviations are 1.6,2.1 and 2.6 cm,respectively,meeting the design requirements.