青龙门大桥防撞套箱施工关键技术
Key Construction Techniques of Collision Protection Casing for Qinglongmen Bridge
摘要 青龙门大桥为(119+231+756+756+231+119)m三塔钢箱梁斜拉桥,桥塔墩承台外侧设置防撞套箱(尺寸为86m×48m×9.8m,总重达2400t).结合工程特点和作业条件,桥塔墩基础采用"先平台后围堰,防撞套箱永临结合兼作围堰"的方案施工,防撞套箱兼作围堰时,专门设计了围堰的内支撑、吊挂系统、底板系统及水平限位装置.在防撞套箱运输前,利用浮吊在内港池码头进行试吊,验证了整体吊装的可行性;在防撞套箱整体装船时,通过浮吊二次抛锚、系缆、绞锚移位实现了外港池码头装船,解决了超大重型防撞套箱装船运输难题;桥位吊装时,通过优化水上施工平台设计、合理安排船舶初始就位与绞锚移位作业时机、快速精确就位、吊挂梁支点反力控制技术,解决了海上高精度吊装难题;施工期间,采用可视化智能吊装与监测预警平台,解决了复杂海况下短窗口期内高效、高精度吊装及安全控制难题.防撞套箱吊装过程中结构受力安全、法兰连接结构可靠;下放到位后实测平面偏差1.5cm,满足设计要求.
Abstract:
The Qinglongmen Bridge is a three-pylon cable-stayed bridge arranged in two main spans of 756 m,two side spans of 231 m,and two end spans of 119 m.The superstructure consists of steel box girders.The pile caps that support the pylon piers are outfitted with vessel-strike protection casings measuring 86 m by 48 m by 9.8 m,with a total weight of 2 400 t.Considering the characteristics of the project and the site conditions,a construction platform was first erected during the construction of the pylon pier foundation.Subsequently,the collision protection casing was installed,which acted as a cofferdam at construction stage and a permanent collision protection component of the bridge at service stage.As a cofferdam,the casing was fitted with temporary inner supports,a suspension system,bottom slabs and horizontal restrainers.Before transportation,the casing was trial-hoisted at the Neigang Dock by a barge-mounted crane to verify the feasibility of integral hoisting.During shipping,measures were taken to allow the components to be shipped at the Waigang Dock,including the secondary anchoring,mooring,and anchor repositioning of the crane,to facilitate the shipment of the heavy and large collision protection casing.The components were hoisted into position offshore with high accuracy,owing to the optimized construction platform,rational arrangement of the initial location of the barge,the proper timing of using the anchor to move the crane,rapid and accurate locating,and control of the reaction forces at supports of the suspended beam.The utilization of a visual intelligent hoisting,monitoring,and early warning platform fueled the success of the highly efficient and accurate hoisting and safety control within the short window time in complicated marine environments.The structure was in a safe load bearing condition,and the flange connection was reliable.The measured plan deviation was 1.5 cm,meeting the design requirements.
刊 名 桥梁建设 ISTICEIPKU
年,卷(期): 2026, 56(4)
分类号: U448.27 U445.556 U445.4
机标分类号: U445.4 U213.6 U656.1
在线出版日期: 2026年9月7日