风电钢-混凝土混合塔筒预应力施工与张拉技术研究
摘要 针对风电钢-混凝土混合塔筒高度大、单束吨位高、体外预应力构造复杂、施工精度要求严苛等特点,结合内蒙古某风电项目 52 台超高混塔工程实践,系统研究装配式混塔体外预应力成套施工技术.通过工厂化集团束下料、高空整体穿束、正交对称分级张拉、应力-伸长值双控、长效防腐封锚等关键工艺,解决超长索体穿束困难、张拉不同步、应力分布不均、伸长值偏差超标等技术难题.工程应用表明,该技术体系可将张拉力偏差控制在 0~+1.5%,伸长值偏差控制在±6%以内,施工效率提升 30%以上,结构受力均匀、安全可靠,可为荒漠、戈壁等恶劣环境下同类型超高风电混塔预应力工程提供成熟技术方案与实践参考.
Abstract:
In response to the characteristics of steel-concrete composite wind turbine towers-such as great height,high tonnage per strand,complex external prestressing structures,and stringent construction accuracy requirements-and drawing on practical experience from the construction of 52 ultra-high composite towers at a wind power project in Inner Mongolia,this paper systematically investigates a complete set of construction technologies for external prestressing of prefabricated composite towers.Through key processes such as factory-based cutting of group bundles,integrated high-altitude cable threading,orthogonal symmetric staged tensioning,dual control of stress and elongation,and long-term corrosion-resistant anchoring,this paper addresses technical challenges,including difficulties in threading ultra-long cables,tensioning asynchrony,uneven stress distribution,and excessive elongation deviations.Engineering applications have demonstrated that this technical system can control tension force deviations within 0 to+1.5%and elongation deviations within±6%,while improving construction efficiency by more than 30%.The structure exhibits uniform stress distribution and is safe and reliable,providing a mature technical solution and practical reference for prestressing projects involving similar ultra-high composite wind turbine towers in harsh environments such as deserts and the Gobi.
年,卷(期): 2026, 55(19)
分类号: TU758.11
机标分类号: TU762 U445.4 TU394
在线出版日期: 2026年10月30日
基金项目: KJ202503:北京市建筑工程研究院有限责任公司青年科技基金课题,