摘要
盾构在复杂土层、高承压水条件下长距离掘进过程中,盾尾刷容易损坏,可能导致盾尾渗漏造成重大安全风险,因此,需要对盾尾密封性进行评估并及时更换盾尾刷来控制安全风险;同时在高承压水环境下更换盾尾刷本身具有较高的安全风险.以某市轨道交通 12 号线穿越长江超大直径隧道工程更换 2 道盾尾刷为例,对复杂地层高承压水条件下更换盾尾刷技术进行了研究.在评估盾尾刷密封性和掘进环境条件的基础上,确定了更换 2 道盾尾刷的总体方案和更换的停机位置;分析了盾尾刷更换风险,制定了详细更换方案并介绍了更换实施过程与要点;对盾构机恢复掘进施工效果进行了评估,结果表明更换效果良好.
During long-distance tunneling by shield machines in complex soil conditions and high confined water pressure environments,the shield tail brushes are prone to damage,which may lead to leakage at the shield tail and pose significant safety risks.Therefore,it is necessary to evaluate the shield tail's sealing performance and promptly replace the shield tail brushes to mitigate these risks.However,replacing the shield tail brushes in high confined water pressure environments itself carries significant safety risks.Taking the replacement of two sets of shield tail brushes in the ultra-large-diameter tunnel project crossing the Yangtze River on Line 12 of a certain city's rail transit system as an example,this paper investigates the technology for replacing shield tail brushes under complex geological conditions and high confined water pressure.Based on an assessment of the shield tail brush sealing performance and the tunneling environment,an overall plan for replacing two sets of shield tail brushes and the specific shutdown locations for the replacement were determined.The risks associated with the replacement were analyzed,a detailed replacement plan was formulated,and the implementation process and key points were outlined.The effectiveness of resuming tunneling operations was evaluated,confirming that the replacement is successful.