军事知识服务平台
特大断面隧道二衬超厚混凝土温度监测及施工关键技术研究
摘要 针对特大断面隧道施工面临的围岩稳定性控制、超厚二衬混凝土温控等技术难题,以某特大断面浅埋 V 级围岩隧道为工程背景,对双侧壁导坑法进行系统性工艺优化.通过将弧形支护改为直墙支护、增设临时竖撑、优化开挖步骤等关键技术,有效提升了施工效率与安全性,降低了工程成本.同时,构建了二衬超厚混凝土温度实时监测系统,精准监控里表温差变化,当温差接近临界阈值时,及时采用保温膜覆盖、土工织物包裹等温控措施,显著减少了温度裂缝的产生,提升了隧道结构的耐久性与整体性.
Abstract:
To address technical challenges in the construction of extra-large-cross-section tunnels such as surrounding rock stability control and temperature control of ultra-thick secondary lining concrete,this paper conducts a systematic optimization of the twin-side heading method,using a specific extra-large-cross-section,shallow-buried,Grade V surrounding rock tunnel as the engineering context.Through key technical measures such as replacing curved support with straight-wall support,adding temporary vertical bracing,and optimizing excavation sequences—construction efficiency and safety have been effectively improved,while project costs have been reduced.At the same time,a real-time temperature monitoring system for the ultra-thick secondary lining concrete was established to precisely track changes in the temperature difference between the inner and outer surfaces.When the temperature difference approached the critical threshold,temperature control measures such as covering with thermal insulation film and wrapping with geotextiles were promptly implemented,significantly reducing the occurrence of temperature cracks and enhancing the durability and structural integrity of the tunnel.
年,卷(期): 2026, 55(19)
分类号: TU755
机标分类号: U455 TU528.07 TU755.8
在线出版日期: 2026年10月30日