软弱围岩隧道系统锚杆支护时机及参数优化研究
Research on optimization of installation timing and parameters of systematic rockbolts in weak surrounding rock tunnels
摘要 为揭示Ⅴ级软弱破碎围岩隧道系统锚杆打设时机及环向布设对支护效能的影响,依托高丘一号隧道,建立考虑施工时序的三维离散元模型,并校核采用多点位移计获得的拱肩竖向位移与水平收敛阶段增量;设置复喷前、复喷后和滞后一个开挖循环的3种打设工况,综合分析围岩位移、初期支护响应、锚杆轴力及塑性区演化,并开展环向布设敏感性分析.现场位移用于模型校核,未实测的支护结构受力指标仅用于数值工况间的相对比较.研究结果表明:随着锚杆打设时机依次推迟,拱顶沉降由24.03 mm增至34.42 mm和43.71 mm,塑性区体积由2 329.59 m3增至3 470.13 m3和5 177.73 m3,较复喷前工况分别增加49.0%和122.1%;0~70°布设范围内普通系统锚杆减配敏感性工况的拱顶沉降为24.31 mm,塑性区体积增幅为2.79%,整体变形对下部普通锚杆减配不敏感,但拱脚局部稳定仍需独立约束.Ⅴ级软弱破碎围岩系统锚杆应在复喷前完成;环向减配仅可在保留锁脚锚管或等效拱脚约束、设置位移预警阈值并明确回退措施的条件下实施.
Abstract:
To clarify the effects of rockbolt installation timing and circumferential layout on the support perfor-mance of tunnels in Grade Ⅴ weak and fractured surrounding rock,a three-dimensional discrete-element model ac-counting for the construction sequence was established for the Gaoqiu No.1 Tunnel.Stage increments of vertical shoulder displacement and horizontal convergence measured with multipoint displacement meters were used for model calibration.Three installation cases—before secondary shotcreting,after secondary shotcreting,and one ex-cavation cycle later—were compared in terms of surrounding-rock displacement,initial-support response,rock-bolt axial force,and plastic-zone evolution,followed by a sensitivity analysis of the circumferential layout.Field measurements comprised displacement only;unmeasured structural-force responses were used solely for relative numerical comparison.Delaying installation increased crown settlement from 24.03 mm to 34.42 mm and 43.71 mm,while the plastic-zone volume increased from 2,329.59 m3 to 3,470.13 m3 and 5,177.73 m3,correspond-ing to increases of 49.0%and 122.1%relative to the pre-shotcreting case.In the 0-70° ordinary-rockbolt reduc-tion sensitivity case,crown settlement was 24.31 mm and the plastic-zone volume increased by 2.79%.The global response was insensitive to the reduction,but independent restraint at the arch feet remained necessary.For GradeⅤ weak and fractured rock,systematic rockbolts should therefore be installed before secondary shotcreting.Any circumferential reduction should be conditional on retained foot-locking pipes or equivalent arch-foot restraint,displacement-based warning thresholds,and explicit fallback measures.
刊 名 现代隧道技术 ISTICPKU
年,卷(期): 2026, 63(5)
分类号: U455
机标分类号: U451.2 TD353.6 TU457
在线出版日期: 2026年11月4日
基金项目: 2025-03:中铁城市发展投资集团有限公司科技创新项目2025-122-006:贵州省交通运输厅重大科技攻关项目GPTJ-18-QJ-01:贵州路桥集团有限公司科技项目HSR202504:高速铁路建造技术国家工程研究中心开放基金课题,